Saudi Binladin Group
Project: Jamarat Bridge & Surrounding Area
Category: Construction Methodology
Project Summary
Introduction
For more than 1,400 years the stoning of the three Jamarat in Muna Valley near Makkah, has been one of the main rituals of Hajj (Pilgrimage). The stoning of Jamarat by pilgrims is repeated daily, in part or in whole, over a 4-day period.
At the beginning, the Jamarat site was marked by three simple monuments on the ground. This allowed the small number of pilgrims to perform the stoning with ease and safety. However, the number of pilgrims started to increase reaching more than three millions in recent years. This large number, mixed with vehicular traffic, resulted in unbearable congestion and increasing reported accidents and casualties. The one-level bridge, completed in 1975, provided needed relief for a maximum of two million pilgrims but proved over the years to be inadequate.
![]()
As a part of the Kingdom’s uncompromising commitment to serve the pilgrims, the last few decades witnessed intensive research and full consideration of all feasible designs leading to awarding Saudi Binladin Group the design and construction of the new Jamarat Bridge and Surrounding Area.
Geometrics
- Overall Length (m) 550
- Maximum Width (m) 100
- Number of Levels 6
- Maximum Clear Span (m) 97
Floor Height (m) 12
Ramps
Number - 19
Total Length (m) - 7,698
Width (m) - 24-42
Total Area (m²) - 217,417Souk Al-Arab Tunnel
Length (m) - 1,850
Width (m) - 34King Faisal Tunnel
Length (m) - 2,250
Width (m) - 16Escalator Buildings:
Number of Building - 11
Number of Escalators - 308Service Buildings & Helipads:
Number of Service Buildings - 6
Number of Helipads - 2Work Quantities
Rock Cut (m³) - 9.04 Million
Shotcreting &Rock Anchoring (m²) - 180,000
Rock Injection (m³) - 5,000
Backfilling (m³) - 825,000
Cast-in-Place Concrete (m³) - 1.17 Million
Precast Concrete (m³) - 1.55 Million
Reinforcement Steel (ton) - 477,400
(for Precast & Cast-in-situ)
Post-Tensioning (ton) - 20,000
Precast Post-Tensioned Concrete Segments (no.) - 5,028
Precast Pre-Stressed Concrete Beams (no.) - 4,214
(up to 38 meter long)
Concrete Paving Tiles (m²) - 590,000
Asphalt Work (m³) - 160,000
Chilled Water Network (m) - 21,000
Waste Water Network (m) - 14,000
Water Supply Network (m) - 26,000
PROJECT MANAGEMENT
The project was a design-build undertaking managed by a fully-dedicated Executive High Committee and Workforce of the Builder. The Project was supervised by the Ministry of Municipalities and Rural Affairs.
RESEARCH MANAGEMENT
Site-specific research has been conducted over more than four decades. It included review of past studies on pedestrian flow and crowd dynamics as well as actual data collection and analysis.
In recent years, the most advanced dynamic pedestrian flow and stoning simulation models were used.
